Status unknown
Bridge joints
Reported via mobile in the Structures (eg bridges, fencing, noise barriers) (NH) category anonymously at 18:29, Sun 21 February 2021
Sent to National Highways less than a minute later. FixMyStreet ref: 2562159.
Bridge joints are high and none have drainage in, I have lots of experience installing these joints and these are appalling
Updates
-
No anti-skid left on these joints meaning that when ive driven over these on my daily commute in wet conditions its causing my vehicle to slip. I used to work for a bridgecare company years ago and have knowledge that joints need to be correctly anti skidded for health and safety purposes
Posted anonymously at 18:01, Mon 22 February 2021
-
Thank you for contacting Highways England. concerning the bridge joints at this location. We are awaiting a report from the contractor who completed these works and will update when we hear back.
Kind regards
Highways England
Posted by National Highways at 16:29, Wed 10 March 2021
-
Thank you for your patience whilst we completed the repairs in relation to your report.
The project manager has stated there are no more works for National Highways to undertake here. Any further issues with the surfacing should be directed towards the local authority.
If you require any further update on this issue our Customer Contact Centre is available 24 hours a day at: • 0300 123 5000
• info@highwaysengland.co.uk
Please quote 21855656 to discuss this matter further.
Kind regards National Highways
Posted by National Highways at 10:19, Mon 15 November 2021
Provide an update
Please note that updates are not sent to National Highways. Your information will only be used in line with our privacy policy