Bridge joints

Reported via mobile in the Structures (eg bridges, fencing, noise barriers) category anonymously at 17:39, Monday 22 February 2021

Sent to Highways England less than a minute later

Bridge joints installed incorrectly, uneven joints. Water sat on top of tarmac indicates drainage not installed in joints.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Working as an operative for the company installing the joints on brockworth bypass last summer. The concrete repairs that needed to be undertaken to the damaged bridge deck, incorrect material was used to do these repairs meaning deck failure will happen again

    Posted anonymously at 17:45, Monday 22 February 2021

  • Thank you for contacting Highways England. concerning bridge joints.

    We shall look into this issue and aim to provide a response by 08/03/21.

    Can we please ask that you check back on this date for an update.

    Kind regards

    Highways England

    Posted by Highways England at 19:21, Tuesday 23 February 2021